TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: PIPELINE CONDITIONS
Post D/T: 11/13/2023 9:33 AM MCT
Notice Eff D/T: 11/13/2023 9:33 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 23-265
Prior Notice: 23-259
Subject: Stage II (8%) Underrun Entitlement Lifted; Underrun Entitlement Warning Reinstated
Notice Text:
Effective Gas Day November 13, 2023, Northwest is lifting the Stage II (8%) Declared Entitlement Period for unauthorized underrun volumes, which was issued in All Shipper’s Notice 23- 259, for all Receiving Parties north of the Kemmerer Compressor Station, and reinstating an Underrun Entitlement warning for all Receiving Parties north of the Kemmerer Compressor Station until further notice.
Northwest has limited balancing flexibility with Jackson Prairie being at 95% full capacity and physical injections currently limited to approximately 275,000 Dth/d for the entire facility. On the south end of the system, Northwest is also subject to injection constraints at the Clay Basin facility. These two factors severely limit Northwest’s ability to absorb banked gas on the system. In lifting the Stage II Declared Underrun Entitlement and replacing it with the Underrun Entitlement warning, Northwest urges shippers to balance their supply and demand needs judiciously to minimize the risk of having to revert back to the more restrictive entitlement stage.
As a reminder and pursuant to Section 14(c) of its Tariff, customer-specific entitlements may be issued to Receiving Parties that:
1) have contributed to the adverse operating conditions for at least two consecutive days; and
2) whose actual measured deliveries have deviated from scheduled deliveries for the previous Gas Day by the greater of 10,000 Dth or 5 percent.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|