Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 24-070
Pegram and Lava CS Recompression Install - Maintenance Reminder posted on Apr 26 2024 7:38AM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  04/26/2024 7:36 AM MCT
Notice Eff D/T:  04/26/2024 7:36 AM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  24-070
Prior Notice:  
Subject:  Pegram and Lava CS Recompression Install - Maintenance Reminder

Notice Text:

As posted in the maintenance schedule on Northwest Pipeline's 
website, Northwest is performing work at the Pegram CS 
beginning Gas Day April 29, 2024 through Gas Day May 02, 2024 
and at the Lava CS beginning on Gas Day May 02, 2024 through 
Gas Day May 06, 2024. The cut point will be the Kemmerer CS 
which will be limited to 585,000 Dth/d northbound. 

If primary nomination requests through the Kemmerer CS exceed 
the available capacity of 585,000 Dth/d northbound (or whatever 
NWP cannot mitigate during any day of the maintenance), 
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in 
Northwest's Tariff, Northwest will give notice of a Declared 
Deficiency Period based on a design capacity of 655,000 Dth/d 
northbound. The deficiency period will continue until the work 
is completed on May 06, 2024. 

Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.


If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.