Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 25-200
Sumner ESD Rescheduled posted on Oct 27 2025 7:39AM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  SUPERSEDE
Notice Type Desc:  MAINTENANCE
Post D/T:  10/27/2025 7:38 AM MCT
Notice Eff D/T:  10/27/2025 7:38 AM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  25-200
Prior Notice:  25-198
Subject:  Sumner ESD Rescheduled

Notice Text:

As posted in the maintenance schedule on Northwest Pipeline's

Website and referenced in Notice ID 25-198, Northwest was

scheduled to perform the Sumner ESD on gas day October 28,

2025, which will now be rescheduled to commence on gas day

October 30, 2025. Northwest is rescheduling this outage to

allow Operations to conduct their work safely due to

potentially inclement weather in the area.

 

The Sumner CS will be limited to 816,000 Dth/d southbound

 

If primary nomination requests through the Sumner CS exceeds

the available capacity of 816,000 Dth/d southbound (or whatever

NWP cannot mitigate during any day of the maintenance),

pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in

Northwest's Tariff, Northwest will give notice of a Declared

Deficiency Period based on a design capacity of 1,033,000 Dth/d

southbound. The deficiency period will continue until the work

has been completed.

 

Please reference the Maintenance Schedule tab at

www.northwest.williams.com for more information.

 

If you have any questions, please call your Commercial Services

Representative or the hotline at 713-215-6301.