Soda Springs ERP Tie-in Part 2 - Maintenance Reminder posted on Aug 28 2025 8:48AM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  08/28/2025 8:45 AM MCT
Notice Eff D/T:  08/28/2025 8:45 AM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  25-137
Prior Notice:  
Subject:  Soda Springs ERP Tie-in Part 2 - Maintenance Reminder

Notice Text:

As posted in the maintenance schedule on Northwest Pipeline's

website, Northwest is performing maintenance at the following

locations:

 

-       Soda Springs CS beginning gas day September 04, 2025,

        through gas day October 10, 2025.

 

The Soda Springs CS will be limited to 388,000 Dth/d northbound

for the duration of the outage.

 

If primary nomination requests through the Soda Springs CS

exceeds the available capacity of 388,000 Dth/d northbound (or

whatever NWP cannot mitigate during any day of the

maintenance), pursuant to Sections 10.2 and 10.3 of Rate

Schedule TF-1 in Northwest's Tariff, Northwest will give notice

of a Declared Deficiency Period based on a design capacity of

652,000 Dth/d northbound. The deficiency period will continue

until the work has been completed.

 

Please reference the Maintenance Schedule tab at

www.northwest.williams.com for more information.

 

If you have any questions, please call your Commercial Services

Representative or the hotline at 713-215-6301.