Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 25-110
Green River ESD&Solar Inspections, Sumner I/O shutdowns, & Oregon City 8600 hr i posted on Jul 31 2025 1:36PM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  07/31/2025 1:34 PM MCT
Notice Eff D/T:  07/31/2025 1:34 PM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  25-110
Prior Notice:  
Subject:  Green River ESD&Solar Inspections, Sumner I/O shutdowns, & Oregon City 8600 hr i

Notice Text:

As posted in the maintenance schedule on Northwest Pipeline's 
website, Northwest is performing maintenance at the following 
locations:

- Green River CS beginning gas day August 04, 2025, through 
        gas day August 08, 2025.
- Sumner CS beginning gas day August 05, 2025, through gas 
        day August 06, 2025.
- Oregon City CS beginning gas day August 06, 2025, through 
        gas day August 10, 2025.

The Green River North Constraint will be limited to 360,000 
Dth/d northbound and 676,000 Dth/d southbound for the duration 
of the outage.

If primary nomination requests through the Green River North 
Constraint exceeds the available capacity of 360,000 Dth/d 
northbound or 676,000 Dth/d southbound (or whatever NWP cannot 
mitigate during any day of the maintenance), pursuant to 
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's 
Tariff, Northwest will give notice of a Declared Deficiency 
Period based on a design capacity of 455,000 Dth/d northbound 
or 761,000 Dth/d southbound. The deficiency period will 
continue until the work has been completed. 

The Sumner CS will be limited to 816,000 Dth/d southbound 
for the duration of the outage.

If primary nomination requests through the Sumner CS exceeds 
the available capacity of 816,000 Dth/d southbound (or whatever 
NWP cannot mitigate during any day of the maintenance), 
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in 
Northwest's Tariff, Northwest will give notice of a Declared 
Deficiency Period based on a design capacity of 1,033,000 Dth/d 
southbound. The deficiency period will continue until the work 
has been completed.

The Oregon City CS will be limited to 240,000 Dth/d southbound 
for the duration of the outage.

If primary nomination requests through the Oregon City CS 
exceeds the available capacity of 240,000 Dth/d southbound 
(or whatever NWP cannot mitigate during any day of the 
maintenance), pursuant to Sections 10.2 and 10.3 of Rate 
Schedule TF-1 in Northwest's Tariff, Northwest will give notice 
of a Declared Deficiency Period based on a design capacity of 
250,000 Dth/d southbound. The deficiency period will continue 
until the work has been completed. 

Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.

If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.