TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 07/09/2025 9:03 AM MCT
Notice Eff D/T: 07/09/2025 9:03 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-097
Prior Notice:
Subject: Burley Solar Inspections, Moab DOT Hydro Test, and Willard I/O – Maintenance Re
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's website, Northwest is performing maintenance at the following locations: - Burley CS beginning Gas Day July 14, 2025, through Gas
Day July 18, 2025. - Pleasant View CS beginning Gas Day July 15, 2025, through
Gas Day July 25, 2025 - La Plata B CS beginning Gas Day July 15, 2025, through
Gas Day July 25, 2025. - Willard CS beginning Gas Day July 16, 2025, through Gas
Day July 17, 2025. The Burley CS will be limited to 514,000 Dth/d northbound for the duration of the outage. If primary nomination requests through the Burley CS exceeds the available capacity of 514,000 Dth/d northbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 579,000 Dth/d northbound. The deficiency period will continue until the work is completed on Gas Day July 18, 2025. For the Moab DOT Hydrotest, the Pleasant View CS will be limited to net 0 Dth/d southbound and the La Plata B CS will be limited to net 0 Dth/d northbound for the duration of the outage. If primary nomination requests through the Pleasant View CS exceeds the available capacity of net 0 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 351,000 Dth/d southbound. The deficiency period will continue until the work is completed on Gas Day July 25, 2025. If primary nomination requests through the La Plata B CS exceeds the available capacity of net 0 Dth/d northbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 283,000 Dth/d northbound. The deficiency period will continue until the work is completed on Gas Day July 25, 2025. The Willard CS will be limited to 380,000 Dth/d northbound and 383,000 Dth/d southbound for the duration of the outage. If primary nomination requests through the Willard CS exceeds the available capacity of 380,000 Dth/d northbound or 383,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 540,000 Dth/d northbound or 431,000 Dth/d southbound. The deficiency period will continue until the work is completed on Gas Day July 17, 2025. Please reference the Maintenance Schedule tab at www.northwest.williams.comfor more information. If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|