Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's website, Northwest is performing maintenance at the following locations:
- Snohomish CS beginning gas day June 23, 2025, through gas day June 27, 2025. - McMinnville CS beginning gas day June 25, 2025, through gas day June 26, 2025.
The Snohomish CS will be limited to 948,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Snohomish CS exceeds the available capacity of 948,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 1,194,000 Dth/d southbound. The deficiency period will continue until the work is completed on gas day June 27, 2025.
The McMinnville CS will be limited to 157,000 Dth/d northbound and for the duration of the outage.
If primary nomination requests through the McMinnville CS exceeds the available capacity of 157,000 Dth/d northbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 207,000 Dth/d northbound. The deficiency period will continue until the work is completed on gas day June 26, 2025.
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.