Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 23-206
Chehalis CS Electrical Work and Sumner CS Electric Start System - Maintenance Up posted on Sep 22 2023 1:36PM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  09/22/2023 1:32 PM MCT
Notice Eff D/T:  09/22/2023 1:32 PM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  23-206
Prior Notice:  
Subject:  Chehalis CS Electrical Work and Sumner CS Electric Start System - Maintenance Up

Notice Text:

As posted in the maintenance schedule on Northwest Pipeline's 
website, Northwest is performing work at the Chehalis 
Compressor Station from September 26, 2023 through October 13, 
2023 and at the Sumner Compressor Station from September 26, 
2023 through October 7, 2023. New capacity restrictions are 
detailed below:

The electrical work at Chehalis Compressor Station will limit 
throughput to 518,000 Dth/day Southbound for the duration of 
the project.

During the Sumner Compressor Station outage, capacity will be 
limited to 724,000 Dth/day Southbound for the duration of the 
project. 

If primary nomination requests through the Chehalis Compressor 
Station exceeds the available capacity of 518,000 Dth/d 
southbound (or whatever NWP cannot mitigate during any day of 
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate 
Schedule TF-1 in Northwest's Tariff, Northwest will give notice 
of a Declared Deficiency Period based on a design capacity of 
602,000 Dth/d southbound. The deficiency period will continue 
until the work is completed on October 13, 2023. 

If primary nomination requests through the Sumner Compressor 
Station exceeds the available capacity of 724,000 Dth/d 
southbound (or whatever NWP cannot mitigate during any day of 
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate 
Schedule TF-1 in Northwest's Tariff, Northwest will give notice 
of a Declared Deficiency Period based on a design capacity of 
960,000 Dth/d southbound. The deficiency period will continue 
until the work is completed on October 7, 2023. 

Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.

If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.