Northwest Pipeline LLC NOTICE #32757 Willard ESD/DOT S/D's & Mt. Vernon Solar Inspections posted on Apr 9 2026 8:53AM TSP Name: Northwest Pipeline LLC TSP: 67977322 Critical: Y Notice Stat Desc: INITIATE Notice Type Desc: MAINTENANCE Post D/T: 04/09/2026 8:39 AM MCT Notice Eff D/T: 04/09/2026 8:39 AM MCT Notice End D/T: Reqrd Rsp Desc: No response required Rsp D/T: Notice ID: 26-045 Prior Notice: Subject: Willard ESD/DOT S/D's & Mt. Vernon Solar Inspections Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest will be performing maintenance at the
following locations next week:
- Willard CS: located at MP 1175.2 in Skamania County,
Washington on gas day April 14, 2026.
- Mt. Vernon CS: located at MP 1440.18 in Skagit County,
Washington beginning gas day April 14, 2026, through
gas day April 15, 2026.
The Willard CS will be limited to 380,000 Dth/d northbound and
383,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Willard CS exceeds
the available capacity of 380,000 Dth/d northbound or 383,000
Dth/d southbound (or whatever NWP cannot mitigate during any
day of the maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 540,000 Dth/d northbound or 431,000 Dth/d
southbound. The deficiency period will continue until the work
has been completed.
The Mt. Vernon CS will be limited to 1,177,000 Dth/d southbound
on gas day April 14, 2026, and limited to 1,240,000 Dth/d
southbound on gas day April 15, 2026.
If primary nomination requests through the Mt. Vernon CS
exceeds the available capacity of 1,177,000 Dth/d southbound on
gas day April 14, 2026, or 1,240,000 Dth/d southbound on gas
day April 15, 2026 (or whatever NWP cannot mitigate during any
day of the maintenance), pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give
notice of a Declared Deficiency Period based on a design
capacity of 1,277,000 Dth/d southbound. The deficiency period
will continue until the work has been completed.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.