All Shippers Letter #08-214
Date: 07/15/08
Time: 04:15 PM MDT
TO: All Shippers
SUBJECT: Lava to Pocatello Anomaly Investigations Extended
Steep terrain and rocky soil conditions have slowed the ongoing anomaly
investigations between the Lava and Pocatello compressor stations. As a
result, the completion date of the project will be delayed from July 31 to
August 10, 2008. The available capacity at the Pocatello compressor station
will remain at 553,000 Dth/d until the project is completed.
If you have questions schedule, please contact your Marketing Services
Representative or call the hotline at (801) 584-7301.