Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 22207
08-070 Expected End of Deficiency Period posted on Mar 6 2008 12:47PM

All Shippers Letter #08-070
Date:  	03/06/2008
Time:  	12:50 PM MST

TO:    	All Shippers

SUBJECT:	Expected End of Deficiency Period at the Cisco Compressor Station

Northwest currently anticipates that the turbine replacement at the Cisco 
compressor station will be completed today. Per Northwest's Tariff, the 
Declared Deficiency Period will end when the design capacity is restored. The 
Cisco compressor station has been set to its South-flow design capacity of 
359,000 Dth/d for the Timely Cycle of Gas Day Friday, March 07, 2008.

If you have any questions, please call your Marketing Services Representative 
or the hotline at 801/584-7301.