TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 06/27/2016 7:29 PM MCT
Notice Eff D/T: 06/27/2016 7:29 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 16-054
Prior Notice:
Subject: Potential Secondary Firm Reductions
Notice Text:
Due to the current southbound flow levels in the Meacham to Kemmerer
corridor, Northwest has moved the maintenance project to upgrade the Boise
compressor station controls from the Unlikely to Impact Schedule to the
Impact Schedule. During this maintenance, which runs from July 6, 2016
through October 25, 2016, Northwest may need to cut secondary capacity down
to the posted operational available capacity of 417,000 Dth/d.
If you have any questions, please call your Marketing Services Representative
or the hotline at 801/584-7301.
NWP
DA/MR
|